Dandy Booksellers Ltd, Suppliers of British Standards, Official and Business PublicationsTelephone Number 0207 624 2993
Product Sections
Civil Service Yearbook
The new Civil Service Yearbook 48th Edition - in stock now.
Civil Service Yearbook 48th Edition available now
Buy The Civil Service Yearbook
IMDG Code 2010/2011
The new IMDG Code is in stock now.
IMDG Code 2010/2011 available now
Buy The IMDG code
New Products

Health and Safety Law Poster (A3 Version)

SI 1885 2011 The Carriage of Dangerous Goods and Use of Transportable Pressure Equipment (Amendment) Regulations 2011

British Pharmacopoeia 2012 - Save £100 off RRP

British Pharmacopoeia 2012 - Save £100 off RRP

£730.00

find out more

UN ADR 2013 European Agreement Concerning the International Carriage of Dangerous Goods by Road (Books)

ADR 2011 and ADR 2013 Pack

ADR 2011 and ADR 2013 Pack

£100.00

find out more

The Official DSA Theory Test for Motorcyclists DVD-ROM 2012 Edition

Foreign Direct Investment 2010, February 2012

International Migration 2010, No.37

ICAO Dangerous Goods Training Manual - Using the Technical Instructions for the Safe Transport of Dangerous Goods Volume 1 (Doc 9375)

ICAO Dangerous Goods Training Manual - Using the Technical Instructions for the Safe Transport of Dangerous Goods Volume 1 (Doc 9375)

£210.00

find out more

Travel Trends 2009

Bookmark us via QR code

NEC3 Engineering and Construction Contract Flow Charts

NEC3 Engineering and Construction Contract Flow Charts
NEC3 Engineering and Construction Contract Flow Charts



£14.25
RRP: £15.00 You save £0.75 (5.0%)




ISBN: 9780727733672
Format: Paper
Publish Date: 01/06/2005
Publisher: Thomas Telford Ltd
Page Size: 297x210mm
Number of Pages: 120

The NEC3 Engineering and Construction Contract Flow Charts enable users to understand the operation of the Engineering and Construction Contract.

This book contains flow charts which set out the procedural logic of the 75 clauses that can be presented with benefit by flow charting.

Contents:
Flow charts
13 Communications
14 The Project Manager and the Supervisor
15 Adding to the Working Areas
16 Early warning
17 Ambiguities and inconsistencies
18 Illegal and impossible requirements
19 Prevention
20 Providing the Works
21 The Contractor’s design
22 Using the Contractor’s design
23 Design of Equipment
24 People
25 Working with the Employer and Others
26 Subcontracting
27 Other (Contractor) responsibilities
30 Starting, Completion and Key Dates
31 The programme
32 Revising the programme
33 Access to and use of the Site
34 Instruction to stop or not to start work
35 Take over
36 Acceleration
40 Tests and inspections
41 Testing and inspection before delivery
42 Searching for and notifying Defects
43 Correcting Defects
44 Accepting Defects
45 Uncorrected Defects
50 Assessing the amount due S
51 Payment
52 Defined Cost
53 The Contractor’s share (Option C and D)
54 The Activity Schedule (Option A and C)
55 The Bill of Quantities (Option B and D)
60 Compensation events
61 Notifying compensation events
62 Quotations for compensation events
63 Assessing compensation events
64 The Project Manager’s assessments
65 Implementing compensation events
70 The Employer’s title to Plant and Materials
71 Marking Equipment, Plant and Materials outside the Working Areas
72 Removing Equipment
73 Objects and materials within the Site
80 Employer’s risks
81 Contractor’s risk
82 Repairs
83 Indemnity
84 Insurance cover
85 Insurance policies
86 If the Contractor does not insure
87 Insurance by the Employer
90 Termination
91 Reasons for termination
92 Procedures on termination
93 Payment on termination
W1 Dispute resolution (used unless Option Y(UK)2 applies)
W2 Dispute resolution (used when Option Y(UK)2 applies)
X1 Price adjustment for inflation (used only with Options A, B, C and D)
X2 Changes in the law
X3 Multiple currencies (used only with Options A and B)
X4 Parent company guarantee
X5 Sectional Completion
X6 Bonus for early Completion
X7 Delay damages
X12 Partnering
X13 Performance bond
X14 Advanced payment to the Contractor
X15 Limitation of the Contractor’s liability for his design to reasonable skill and care
X16 Retention (not used with Option F)
X17 Low performance damages
X18 Limitation of liability
X20 Key Performance Indicators (not used with Option X12)
Y(UK)2 The Housing Grants, Construction and Regeneration
Act 1996
Y(UK)3 The Contracts (Rights of Third Parties) Act 1999






Related Publications:

NEC3 Engineering and Construction Contract

NEC3 Engineering and Construction Contract

NEC3 Engineering and Construction Contract Guidance Notes ECC

NEC3 Engineering and Construction Contract Guidance Notes ECC

NEC3 Engineering and Construction Contract Option B: Priced contract with bill of quantities

NEC3 Engineering and Construction Contract Option B: Priced contract with bill of quantities



Main Pages
ADR 2011
Worldwide Delivery
Secure Payment
Secure Payment
Follow Us On Twitter

Best Sellers

ADR 2011 The European Agreement concerning the International Carriage of Dangerous Goods by Road (Books)

IMDG Code 2010/2011 (Book) 2 Vols

Civil Service Yearbook 48th Edition 2011/12

HSE Approved Codes of Practice - Six Pack (6 Pack) Pack of 6 Books

ADR 2011 The European Agreement concerning the International Carriage of Dangerous Goods by Road (Book and CD Pack)

ADR 2011 The European Agreement concerning the International Carriage of Dangerous Goods by Road (Book and CD Pack)

£137.70

find out more

Rules and Guidance for Pharmaceutical Manufacturers and Distributors 2007 -Book

PSA Schedule of Rates for Building Works: Tenth Edition

PSA Schedule of Rates for Building Works: Tenth Edition

£243.00

find out more

HSE L144 Managing Health and Safety in Construction

HSE HSG6 Safety in working with lift trucks

Section Link Directory